Comparing the original schedule submitted to the Supreme Court by NCA and actual work done, it is evident that the project is two years behind the schedule. Any further delay would mean severe loss to the nation. At present construction is taken up for raising the dam height from 110.64 meter to 121,90 meter height. Storage of water starts only above 110.64 meter height of the dam. Hence till such time darn is at 110.64 meter height, water supply would remain dependent on the flow of water in the river Narmada which fluctuates heavily and therefore water supply for irrigation and drinking purposes cannot be assured. Therefore if the darn is not raised to 121.90 meter height, there would be loss in storage of water of about 157 crore cubic meter which would mean loss in irrigation to 3.5 lac hectares of iand, of which loss of benefit to Gujarat would be 3 lac hectares and that to Rajasthan would be 0.5 lac hectares,
Further there would be loss in power generation to the tune of 350 crore units equivalent to Rs. 1400 crore. Of this, share of the state of Madhya Pradesh would be 57%, Maharashtra 27% and Gujarat 16% as per Tribunal's Award.
Rs. 20,973 crores have been invested on this project uptill now. The cost of interest is mounting with every day passing. Annual interest burden is of the order of Rs. 900 crores.
Status of implementation of Court orders re. R& R
It is important to note that on 15 th March 2005 the Supreme Court issued an order to the Government of Madhya Pradesh to consider major sons of the landowner Project Affected Families as separate families and to extend to each major son, full benefit of rehabilitation package. The Court also ordered that all the applicants who were both temporarily and permanently affected by submergence by reason of raising the height of the dam to the present height would be entitled to the benefit of rehabilitation package.
Government of Madhya Pradesh has completed resettlement and rehabilitation (R & R) of Project Affected Families conforming to the Directions given under Narmada Water Disputes Tribunal's Award, Orders of the Supreme Court as well as the Directions given by respective Grievance Redressal Authorities (GRA).
Observations of Supreme Court re. stoppage of work
The Supreme Court in its judgment dated 18 th October 2000 has observed as under:
"The Award of the Tribunal is binding on the States
concerned. The said Award also envisages the relief
and rehabilitation measures which are to be
undertaken, if for any reason, any of the State
Governments Involved lag behind in providing
adequate relief and rehabilitation then the proper
course, for a Court to take, would be to direct the
Award's implementation and not to stop the execution
of the project. This Court, as a Federal Court of the
country specially in a case of inter-State river dispute
where an Award had been made, has to ensure that
the binding Award is implemented. In this regard, the
Court would have the jurisdiction to issue necessary
directions to the State which, though bound, chooses
not to carry out its obligations under the Award. Just
as an ordinary litigant is bound by the decree,
similarly a State is bound by the ward. Just as the
execution of a decree can be ordered, similarly, the
implementation of the Award can be directed. If there
is a short fall in carrying out the R&R measures, a
time bound direction can and should be given in order
to ensure the implementation of the Award. Putting
the project on hold is no solution...... " |